August 26, 2022
Supply of line hardware, installation and commissioning of extensions of MV lines, LV single phase lines and service cables for electrification program in the counties: Kilifi, Kwale, Lamu, Mombasa, Taita Taveta, Tana River
Kenya Power and Lighting Company Limited (KPLC) |
Kenya |
09/11/2017 |
Consistency
Supply of line hardware and installation of:
60 km of MV lines (33 KV and 11 KV)
102 distribution transformers 50 KVA
1012 km of LV lines
32950 service cables and meters
21750 ready boards